Taylor Wimpey have issued a programme of works that will enable the link bridge between Old Park Farm / Wellington Vale and Berewood to be opened for use in August 2017.
May – electrical mains laying and street light completion
June – Completion of side A (shared pedestrian-cycle way and road) and bridge inspection by Hampshire County Council
July – Remedial works to be undertaken and approved (if applicable by Hampshire County Council)
August – Road bridge and side A to be opened
March 2018 – Side B (footpath) to be opened once residential Phase 5 is complete
Once the link bridge is opened the access through Sickle Way will be closed for general access by bollards. The work to install the bollards is scheduled to take place in July 2017.
Completion works will take place at the junction of Hambledon Road and Darnel Way from 4th May for approximately 4 weeks.
Final surfacing for the rest of Darnel Road to the Household Waste Recycling Centre is scheduled for March 2018.